Red Eagle Trail Project

  • Completion DateAugust 12, 2026

The City of Hudson Oaks will begin resurfacing a section of Red Eagle Trail on August 3 to improve pavement conditions and provide a smoother, safer roadway for motorists.

Project Schedule

  • Project Start: August 3
  • Estimated Completion: August 12
  • Work Hours: Monday–Friday, 7:00AM – 6:00PM

Traffic Impacts

During construction, traffic will be reduced to one lane with alternating lane closures to allow crews to safely complete the work. Motorists should expect delays and are encouraged to plan ahead when traveling through the area.

While work is expected to be completed as scheduled, please be prepared for possible delays if additional work is required.

Please reference the project map to view the section of Red Eagle Trail that will be resurfaced.

Safety Reminder

Please slow down, follow all posted traffic control devices, and watch for construction crews and equipment in the work zone.

The City of Hudson Oaks appreciates your patience and cooperation as these roadway improvements are completed.

 